Connect four solar power plants to the grid and put them into operation in Tartus
Within the framework of the government's tendency to benefit from renewable energy projects to ensure electricity security and strive to increase the percentage of
Its contribution to energy balance, especially in the industrial sector,in ensuring energy security.
The total power of the four stations established in several stages is 18588/MW:
-The first location: Iron Center and Farm, with a capacity of 6200/KF
-Second location: Amra – Safita can handle/5000 KF
-The third location: Savaka School in Tartus, with a capacity of 2900/KF.
-Fourth location: Phoenix School – Tartus, number 4488/KF
It is worth noting that the project is expected to generate an annual electricity output of 18588
1600=29740 cubic meters.
It is worth noting that the project is expected to generate an annual electricity output of 18588
1600=29740 cubic meters
The approximate cost of this project is: 6 billion LS/MW installed capacity
Eng Zamil also visited the newly established Syrian photovoltaic clamp production company in Latakia and emphasized its importance.
On the one hand, these industries have contributed to the implementation of the Ministry's strategy of relying on renewable energy,
On the other hand, promoting the economic reality of post-war Syria, overcoming the difficulties faced by investors by importing solar panels.
Zamir praised the national expertise from the manufacturing stage to final testing, as well as advanced equipment.